Three modules of the first shipment with a total approximate weight of 5,800 ton had been completely loaded out to the ship through Terminal C0 of Laem Chabang Port on February 27, 2015. The modules will be transported to the site at Blaydin Point in Darwin, Northern Territory in Australia for installation. The next milestone
- Published in Press News
Forbes Asia Best Under A Billion Forum
12 December 2014
“On behalf of the dedicated team who are working so enthusiastically to further improve the reputation of STP&I Public Company Limited, Khun Masthawin Charnvirakul represented the company at the Forbes Asia Best Under A Billion Forum & Awards Dinner on the 9th of December 2014. As a company we feel so honored to be one
- Published in Press News
Progress of STP&I Ichthys Project Update June 2014
13 June 2014
The STP&I’s module assembly work for Ichthys Onshore LNG Facilities Project is progressing as planned with significant progress at every facility. The structural steel and piping fabrication at Chonburi Shop, Rayong Shop and Sriracha Shop achieved over 50% progress. Most of the fabricated structural steel and fabricated pipe have been delivered to Laem Chabang Yard
- Published in Press News
Last Shipment of QC LNG Project Sail Away
25 September 2013
Queensland Curtis LNG Project which has been operated at STP&I Laem Chabang Module Yard loaded out the last module weight 1,292 tons on September 23, 2012 at C0, Laem Chabang Port, Thailand for shipping out to site in Queensland, Australia.